1. It is a coalition of churches in our community coming together to build a home with Habitat for Humanity. This undertaking recalls the Apostles of Jesus and brings congregations together to raise the funds, hammers and prayers necessary to create a home.
APOSTLE BUILD CHAIR WHAT CHURCHES NEED TO DO Provide a Project Director as a point of contact between Habitat and the church. Raise $5,000 to be donated to GFAHFH by April, 2007. Provide prayer support for the family, for the building of the home and safety of the volunteers.
Provide volunteer assistance with on site labor and/or provide lunches to on site work teams.
May 7th – May 25th: Clean excavation hole, compact, build footing forms and pour, foundation walls: tie rebar, pour, sack, smooth, waterproof and insulate with blue foam, install center beam and sill plates. Vapor barrier crawl space.
May 25th – June 20th: Install floor joists, sheath the decks and trim the edges. Frame and sheath exterior walls and headers, stand and brace. Install top plates. Frame interior walls. Place sheets of vapor barrier on top sills of interior walls (before trusses are set). Build deck and steps. Build steps into crawl space. Drill holes for electrical in studs, Install hold downs and insulate rim joists. Install pre-formed flashing and finish backfill to grade. Install bath tub. Install wood strips around window openings.
June 20th – July 14th: Set trusses, build out-riggers, sheath roof, truss bracing, hurricane ties, baffles and install fascia. Install blue foam up to gables. Install foam or wood strips on gable ends. Install house wrap. Cut thresholds for entryways. Install windows and doors. Install extra blocking in walls needed for cabinets, range hood
July 14th – August 1: Install vinyl siding. Install gable vents. Install dryer vent, stove hood vent and bathroom vent to outside. Drill holes for HRB intake and exhaust vents. Dig wells and line with decking material. Caulk penetrations and around windows. After rough-in inspection, install insulation, vapor barrier and sheetrock. Finish out boiler room (tape, texture, paint, vinyl flooring).
August. 1st –10th: Get caught up on any exterior things that aren’t done yet, before it gets any colder! Do dormant seeding for lawn. Cut fresh air vent for boiler room. Install edging, hinge and pull for crawl space hatch. Paint interior walls.
August. 10th –August 25th: Cut, sand, stain and install window sills. Clean floors well and install underlayment. Volunteers can install vinyl if skilled enough. Install bath vanity, toilet, sinks, faucets, medicine cabinet, towel bars, etc. Install kitchen appliances after cabinets are in. Install range hood and build a chase for the vent. Install interior door frames,
August 25th – September 8thth: Hang interior doors and closet doors after carpet is laid. Install house numbers, door hardware. Punch list, cleaning, putting away tools. September 9th: Tentative date for Home Dedication